Missions of MLF Division
MLF division implements the following items to gain maximum output in such
fields of materials science, life science and so on by the use of J-PARC.
1) Construction of the pulsed neutron source, the pulsed muon source, neutron
and muon instruments in MLF.
2) Operation and maintenance of components, devices and appalatus in MLF.
3) Technology development and research for maintaining and improving operational
techniques and performances of instruments in MLF.
4) Technical supports for users to enable them to produce high quality
outputs.
5) Leading edge scientific research and development for maximizing the
MLF's performance and improving the potential of facility.
|
|
@Materials and life science facility building has been completed
on April 20, 2007 since the construction started in the beginning of 2004.
Along with the building construction, installations of neutron source and
muon target components have been carried out using large scale cranes in
the MLF building.
The neutron source and muon target components are in the final stage
of installation procedure since their manufacturing and installation started
from 2004. The commissioning tests of those components are also under progress
towards the first beam delivery date scheduled in May 2008. The proton
beam transport line (BT) components have almost finished its commissioning
for the forthcoming 3GeV RCS's beam commissioning in September, 2007. The
rest of BT components are still in the commissioning test. On the other
hand, the neutron instruments are in the midst of construction phase. |