   NEW RESEARCH LIFE WITH COVID-19 AT J-PARC.

2. [Accelerator Division]

   OPERATION STATUS OF THE ACCELERATORS.

3. [Particle and Nuclear Physics Division]

   FIRST BEAM AT THE NEW BEAMLINE IN HADRON EXPERIMENTAL FACILITY.
   NEW RESULTS ON THE NEUTRINO CP PHASE
   AND THE SARUHASHI PRIZE TO A. K. ICHIKAWA.
   STATUS OF THE COHERENT MUON TO ELECTRON TRANSITION (COMET).
   STATUS OF THE MUON G-2/ ELECTRIC DIPOLE MOMENT. (EDM) (E34).

4. [Materials and Life Science Division]

   GREETING FROM THE NEW LEADER OF THE MATERIALS AND LIFE SCIENCE
   EXPERIMENTAL FACILITY (MLF) DIVISION.
   BEAM POWER WAS RAISED TO 600 kW.
   MLF IS CALLING GENERAL USE PROPOSALS FOR THE ROUND 2020B+2021A.
   CONSTRUCTION OF ELECTRIC POWER SUBSTATION FOR H-LINE COMPLETED.

5. [Nuclear Transmutation Division]

   MEASUREMENT OF DISPLACEMENT CROSS-SECTION FOR PROTON BEAM
   INTERCEPTING MATERIAL.

6. [Safety Division]

   THE APPLICATION FOR A LICENSE OF THE OPERATION WAS GRANTED.
   THE SAFETY INSPECTION WAS SUCCESSFULLY CONDUCTED.

7. [Editorial Note]

 

---------------------------------------------------------------------
1. [Overview] by Naohito SAITO
---------------------------------------------------------------------

 NEW RESEARCH LIFE WITH COVID-19 AT J-PARC

     We hope you all are doing well and healthy under still expanding
gloom. As reported in the previous issue, we have managed to restart
the operation of J-PARC in mid-May. Since then, we have fully opened
the facility for users, while some domestic users still had travel
restrictions from their own institutions.
     The operation ended as of June 27, and we have now entered into
summer maintenance. Even during a short period of operation, we were
able to make progress of the facilities entering into a new phase of
J-PARC: a new beamline in the Hadron Experimental Facility (HEF) started
its operation to accommodate immediately user experiments, and high
power operation of Material and Life experimental Facility (MLF) was
successfully performed with most of the beamline operated at "1 MW (1)"
for 36.5 hours. These accomplishments are described by those
facilities later in this issue.
     While we are editing this issue, a confirmed number of positive
cases started to increase in Japan. We have been updating our measures
to prevent us from infections through the discussions at the Special
Measures Taskforce, co-headed by Dr. Ishii, the deputy director of
J-PARC for safety and myself. The latest message can be found at
https://j-parc.jp/c/j-parc-covid/index.html (Japanese) and
https://j-parc.jp/c/en/j-parc-covid/index.html (English).
     The message is not only for staff and users, but also for the
contractors who are increasingly important during the maintenance.
We are asking for physical distancing, wearing facial masks properly
in talking, cleaning and washing hands thoroughly, and getting fresh
air regularly. Now we have added the counter measures for heatstroke,
since wearing mask tends to increase body temperature.
     With all these possible measures to protect users, ourselves, and
anyone working at J-PARC, which might be overdoing, we will make our
best efforts to keep our facility open for research and education
as much as possible even with upcoming next waves. We will proactively
update our measures reflecting the up-to-date knowledge on COVID-19
and relevant information and share with users and contractors through
our homepage.
     Stay healthy and we are looking forward to seeing you at upcoming
beam time after summer shutdown at J-PARC!

(1) The operation power of 1 MW means the power of beam accelerated
at Rapid Cycle Synchrotron (RSC), and typical power received at MLF
was 0.92 MW due to bunches extracted for further acceleration at the
Main Ring (MR).

 

---------------------------------------------------------------------
2. [Accelerator Division] by by Michikazu KINSHO
---------------------------------------------------------------------
 
 OPERATION STATUS OF THE ACCELERATORS

     The beam operation as an operation run of Run#84, which started
in January, continued until April 20th, when it was stopped for COVID-19.
The scheduled outage was May 1st. The user program was executed in
only the Materials and Life Science experimental facility (MLF), at a beam
power of 500 kW, because licensing for a new target and a new beam
line in the HD was delayed from the Authority and beam operation was
postponed. A new operation run was started on May 11th, we started the user
program for the MLF at a beam power 500 kW which was the same as
the previous Run#84 on May 15th, and the beam power was increased to
600 kW from May 18th. The user program was carried out as scheduled
until June 27th, and it was successfully executed with a beam power of
1 MW from June 25th to 27th. The user operation for the MLF ended on
June 27th followed by the six days of accelerator study before the summer
shutdown.
     After the shutdown, we will start linac tuning on October 25th
followed by the RCS tuning. The user program of the MLF will start on
November 9th.
     For the Main Ring synchrotron (MR), the beam delivery to the
Hadron experimental facility (HD) was started at small beam power on
May 28th. After the fine tuning of the MR, we delivered beam at
around 51 kW, which was the similar level as the previous operation.
The HD user program was executed on June 25th and 26th at a beam
power of around 51 kW, and one day beam study was carried out after
HD user program. The MR operation was completed on June 27th until
after the summer shutdown.

 

---------------------------------------------------------------------
3. [Particle and Nuclear Physics Division] by T. TAKAHASHI and K. OZAWA
---------------------------------------------------------------------

 First beam at the new beamline in Hadron Experimental Facility
(by H. Takahashi, Y. Komatsu, K. Ozawa)

     We had beam time from May 23 to June 25 for the Hadron
Experimental Facility. During the beam time, we succeeded in having
the first beam to a new beamline. The new beamline was constructed
to deliver primary protons to experimental areas and experiments can
use primary protons directly. This is the first case to use primary
protons directly for experiments at J-PARC.
     The beamline was implemented as a branch of the existing
beamline. A very tiny fraction (0.05%) of the primary beam is
separated and transported into the south part of the Hadron
experimental hall. The intensity of the new beamline is 10^10 protons
per spill and it is high enough for direct uses by experiments. Beam
tunings were carefully performed at the beginning of the beam time.
We adjusted beam positions and profiles and increased the beam intensity
gradually. Finally, we succeeded in having the designed beam intensity
and a minimum loss of the beam. An official inspection for radiation
safety issues was done on June 22 and the new beamline started its
operation. A new experiment to study modifications of mass spectra of
vector mesons in a nucleus was started at the new beamline.
     In parallel, we performed a Sigma-Nucleon scattering experiment
at the K1.8 beamline and measurements of K_L to pi0 nu nu-bar
experiment at the KL beamline.

  NEW RESULTS ON THE NEUTRINO CP PHASE
AND THE SARUHASHI PRIZE TO A. K. ICHIKAWA
(by T. Matsubara)

     In April, the T2K collaboration published new results in the
scientific journal Nature placing the strongest constraint on the
leptonic CP violating phase in neutrino oscillation. CP violation in
the neutrino sector provides a hint to explain the matter-antimatter
imbalance of the universe.
     Theoretically, the phase can take any value from -180 deg to
180 deg and the actual value is not yet known. T2K evaluated the
confidence intervals for the phase, by analyzing data with 1.49x10^21
(neutrino beam mode) and 1.64x10^21 (antineutrino beam mode) protons
on target from the accelerator.
     The data is most compatible with a value close to -90 deg and the
disfavored region at the 99.7% (3 sigma) confidence level is almost
half of the possible region: -2 deg to 165 deg. The CP symmetry
(0 deg and 180 deg) is disfavored at the 95% confidence level, which
is consistent with previous results in 2018. This result is a major
step forward to know whether neutrinos and antineutrinos behave
differently.

     A. K. Ichikawa (Kyoto Univ.), a current spokesperson of the T2K
collaboration, was awarded the Saruhashi prize 2020 that is an annual
prize to a woman researcher in the field of natural science
(http://www.saruhashi.net/index.html, only in Japanese). The research
theme for the award is "unraveling the nature of neutrino by
accelerator-based long baseline neutrino experiment".

Recent Publications

o Constraint on the matter-antimatter symmetry-violating
   phase in neutrino oscillations, K. Abe et al.
   https://www.nature.com/articles/s41586-020-2177-0

o First combined measurement of the muon neutrino
   and antineutrino charged-current cross section
   without pions in the final state at T2K, K. Abe et al.
   https://dx.doi.org/10.1103/PhysRevD.100.112009

o Simultaneous measurement of the muon neutrino
   charged-current cross section on oxygen and carbon
   without pions in the final state at T2K, K. Abe et al.
   https://doi.org/10.1103/PhysRevD.101.112004

 STATUS OF THE COHERENT MUON TO ELECTRON TRANSITION (COMET)
(by S. MIHARA)

     The COMET experiment aims to search for the lepton-flavor
violating muon reaction, mu-e conversion, with sensitivity better
than 10^{-14} in Phase I.
     After completing winding of all coils for the capture solenoid in
JFY2019, we started assembling them to two larger coils by connecting
them mechanically, electrically, and thermally. Once this assembly work
finishes, the cold mass will be installed into a large cryostat for
cooling down to the liquid helium temperature. Close communication with
the manufacturing factory continues until we complete the production.

     A new proposal to measure the 8 GeV proton beam extinction factor in
advance of the COMET phase-I has been submitted. We plan to conduct
this measurement with a new accelerator configuration established after
long discussion with the J-PARC accelerator team based on the result
obtained in the previous test. The expected sensitivity of the
extinction factor measurement is 4x10^{-12}.

     The collaboration had a collaboration meeting fully by
videoconference in June 29 - July 3 as we still suffer from the
COVID-19 effect. Duration of the meeting of each day was shortened
to cope with the time differences of collaboration members from
different countries. Nevertheless, active discussion was made to
maintain the experiment group activity, and the schedule toward the
start of phase-I was updated.

 STATUS OF THE MUON G-2/ ELECTRIC DIPOLE MOMENT. (EDM) (E34)
(by T. MIBE)

     The E34 collaboration prepares for precision measurements of the
muon anomalous magnetic moment and electric dipole moment. The muon
g-2 theory initiative released a white paper in arXiv where a single
value for muon g-2 in the standard model is given. It appears the
discrepancy from the BNL experiment is at a level of 3.7 standard
deviations. The collaboration held a collaboration meeting to discuss
global plan of the experiment by using a video conference system in
June 17-18.
     Demonstration of laser ionization of muonium for the thermal
energy positive muon source is in preparation. A test experiment to
ionize hydrogen atoms was successful in KEK Tsukuba campus. The
experimental setup is being upgraded for the upcoming experiment at
J-PARC. A paper on muonium production was submitted.
     Preparations for 1 MeV acceleration of muon with RFQ and IH-DTL
are in progress at J-PARC linac bldg. Testing of DAW (Disk And Washer)
cold model for middle range velocity is in progress.
   The three-dimensional beam injection has been studied with low
energy electron beam by KEK and Ibaraki University. A kicker system
for beam storage was developed.
     The silicon tracking detector is being assembled at KEK mechanical
engineering center in collaboration with Kyushu University. A paper on
front-end electronics was submitted. Software framework with simulation
package was released. Tutorial lectures on the software framework were
given to the collaboration. A high statistics production of end-to-end
simulation data is being prepared.

 

---------------------------------------------------------------------
4. [Materials and Life Science Division] by Toshiya OTOMO
---------------------------------------------------------------------

 GREETING FROM THE NEW LEADER OF THE MATERIALS AND LIFE SCIENCE
EXPERIMENTAL FACILITY (MLF) DIVISION

     I assumed leadership of the MLF division in J-PARC on April 1,
2020 as a replacement for the former division head, Prof. Toshiji
Kanaya. It has been more than 10 years since the first beam in 2008
and I think that it is now the time to clarify a 10 years vision of MLF
for producing the world's top outcomes in science and industrial applications
with neutron and muon. I am more than happy to have an occasion to
work with MLF staff and users in the world to produce excellent outcomes.

Toshiya Otomo
Head of the Materials and Life Science Experimental Facility Division

  BEAM POWER WAS RAISED TO 600 kW
1) Neutron Source
     The beam operation of MLF is going on with the daily availability
of 93.7% on average since April 1, as of June 27 in 2020. The beam
operation was forced to be stopped from April 20 to May 15 due to the
coronavirus pandemic. After the beam operation was resumed, the beam
power was raised from 500 kW to 600 kW on May 18.
     At the end of this run time, 1 MW beam operation with the duration
of 36.5 hours was held from June 25 to 27 which is much
longer than the 1 MW operation of 10.5 hours last year. Much facility
data of high-power operation were obtained.

 MLF IS CALLING GENERAL USE PROPOSALS FOR THE ROUND 2020B+2021A

     2) Neutron Instruments and Science
     MLF beam operation has been paused on April 20 taking into
consideration the request of the Japanese government for controlling
spreading infection of COVID-19 (declaration of a state of emergency).
The declaration was lifted on May 14, and MLF decided to resume the
beam operation on the next day 15. We started from the in-house staff
work, then opened for the users step by step. Until the end of May,
MLF activities are almost fully opened for domestic users.
     All the MLF user experiments scheduled on the round 2019A, 2019B
and 2020A which are yet to be carried out partly due to the delay of
beam delivery after the long shut down in November 2019 and partly
due to the COVID-19 pandemic can be postponed (carried over) but will
expire in the end of fiscal 2020 (March 31, 2021) without further
extension.
     The upcoming MLF proposal round 2020B combined with 2021A is
called during June 17 to July 15, which is two months behind the usual
schedule (URL: https://mlfinfo.jp/en/user/proposals/2020B2021A/).
     Many symposia, conferences and workshops have been cancelled in
this period all over the world. MLF plans to organize two major
international workshops, DENIM (The 9th annual Design and Engineering
of Neutron Instruments Meeting) and ISSE Workshop (11th International
Workshop on Sample Environment at Scattering Facilities), they both
are strongly important and related to neutron instrumentation and
techniques. These two series of workshops were postponed to September
in 2021.

 CONSTRUCTION OF ELECTRIC POWER SUBSTATION FOR H-LINE COMPLETED

     3) Muon Science Facility (MUSE)
     The H-line is one of the four branches of muon beamlines envisaged
in the original plan of MLF, located next to the S-line in experimental
hall No. 1. While it has been in a status of limbo for years, the J-PARC
headquarters provided partial support every year since 2016 for
putting the plan forward. The support was used for building the new
electric power substation needed to meet the huge demand of electricity
expected for the H-line operation. The construction work underwent
steady progress for the past three years, and all the civil engineering
works and cabling through the MLF building were finally completed
towards the end of FY2019. This marks a major milestone in realizing
the H-line, and now it is planned in the coming summer shutdown period
to complete the minimal equipment required for muon beam delivery to
the H1 experimental area.

 

---------------------------------------------------------------------
5. [Nuclear Transmutation Division] by Shin-ichiro MEIGO
---------------------------------------------------------------------

 MEASUREMENT OF DISPLACEMENT CROSS-SECTION FOR PROTON BEAM INTERCEPTING
MATERIAL

     For the accelerator-driven system (ADS), beam intercepting
material such as a beam window plays an important role. To evaluate
the displacement damage of materials irradiated with the proton beam,
displacement per atom (dpa) is widely utilized as a damage index,
which is estimated by displacement cross-section and particle flux.
Although the dpa is widely employed as a damage index, the displacement
cross-sections for the proton energy employed in the ADS, especially for
a beam window made of iron, is unknown. Therefore, we carried out the experiment
of measurement of the displacement cross-section at J-PARC using 3 GeV
proton synchrotron (RCS).
     Since the electrical resistance increases by the displacement in
the metal, the displacement cross-section can obtain from the
resistivity change of the sample owing to the proton irradiation. To
sustain the defect created by the irradiation, the sample was kept
under the cryo-temperature (4 K). After a series of measurements,
displacement cross-sections of iron were obtained, which are the
first experimental data in the world in the energy range applied to
the ADS.
     With the experimental data, the calculation model for displacement
was validated. The Norgett−Robinson−Torrens displacements per atom
(NRT-dpa) model widely utilized for the estimation displacement was
found to give about 2 times larger than the experiment. On the other
hand, the cutting edge model, athermal recombination correction (arc)
based on the molecular dynamics simulation, showed good agreement
with the experiment.

 

---------------------------------------------------------------------
6. [Safety Division] by Kotaro BESSHO and Yoshihiro NAKANE
---------------------------------------------------------------------
 
THE APPLICATION FOR A LICENSE OF THE OPERATION WAS GRANTED

     The application for changes of the radiological license was
granted by the Nuclear Regulation Authority (NRA) on April 28. The
approved changes in the application were the power-up and a new
primary beam line in the Hadron Experimental Facility and the minor
change of the radiation controlled area of the Neutrino Experimental
Facility.

THE SAFETY INSPECTION WAS SUCCESSFULLY CONDUCTED

     The safety inspection of the Hadron Experimental Facility (HD)
was successfully conducted, and the certificate was issued on June 24
by Radiation Management Institute, Inc. The inspection items were the
shielding construction prepared for a new primary beam line, the
measurement of radiation dose rates around the shielding construction,
and the operation tests on the safety interlocks in HD.

 

---------------------------------------------------------------------
7. [Editorial Note]
---------------------------------------------------------------------

Past issues are available from the below link.
http://j-parc.jp/c/en/topics/project-newsletter/index.html

 

++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Editorial Board:
Toshifumi TSUKAMOTO (Chair): toshifumi.tsukamoto@kek.jp
Kaoru SHIBATA: shibata.kaoru@ jaea.go.jp
Taketoshi MORISHITA: morishita.takatoshi@jaea.go.jp
Dick MISCHKE (English Editor): mischke@triumf.ca
Keiko NEMOTO (Secretary): nemoto.keiko@jaea.go.jp
++++++++++++++++End of Letter++++++++++++++++++++++++++++++++++++++++