J-PARC Newsletter Hilight
ACCELERATOR KEEPS AVAILABILITY HIGHER THAN 92 % IN USER OPERATIONS FOR NEUTRON, MUON AND NEUTRINO.---more (J-PARC Project Newsletter No.41, Aug.4, 2010)
AVAILABILITY EXCEEDS 92 % IN 120 KW OPERATION FOR THE
COMMON USE OF MLF (MATERIAL AND LIFE SCIENCE FACILITY).---more (J-PARC Project Newsletter No.40, June.8, 2010)
THE FIRST T2K NEUTRINO EVENT OBSERVED AT SUPER-KAMIOKANDE
---more
(J-PARC Project Newsletter -Special Issue-, Mar. 5, 2010)
SUCCESS IN 300 kW TEST OPERATION OF RCS (3-GeV Rapid Cycling Synchrotron) ---more (J-PARC Project Newsletter No.39, Mar. 1, 2010)
Beam commisioning restarted with steady improvement of
RFQ (Radio-Frequency Quadrupole) LINAC---more
(J-PARC Project Newsletter No.38, Nov. 13, 2009)
Success of Extraction to Neutrino Target from MR---more (J-PARC Project Newsletter No.37, July 23, 2009)
Extraction of 30 GeV proton beam to hadron beam dump---more (J-PARC Project Newsletter No.36, May 7, 2009)
Success of 30GeV acceleration and extraction in MR
---more (J-PARC Project Newsletter No.35, Feb. 4, 2009)
EXCITING NEWS FROM THE 3 GEV ACCELERATOR April15, 2008
J-PARC Project Newsletter #32(April15, 2008) [Overview] by Shoji NAGAMIYA
At the end of October we had a successful acceleration in the
3 GeV ring. Four months later, at the end of February of 2008, the beam power per pulse reached 5 kW/pulse. Since the 3 GeV ring will operate at 25 Hz (25 pulses per second), this power/pulse is equivalent to 130 kW per second if 25 pulses were accelerated.
Since the neutron target is not yet ready to accept the primary proton beam, the accelerator crew decided to deliver 50 kW beams to a beam dump for about four minutes before the accelerator operation was terminated for the March shutdown for machine inspection. We had not expected to reach such a high power level within the first four-month period after the injection and extraction were achieved at 3 GeV. It is, therefore, exciting news for us.
Note that the goal at 3 GeV is 600 kW by using the present Linac energy and 1 MW by boosting the Linac energy to 400 MeV.
J-PARC Project Newsletter #32 April 15, 2008
ONE SHOT OF 1.07E13 PROTONS WAS EXTRACTED FROM THE RCS AT 3 GeV, WITH A MODEST BEAM LOSS, CORRESPONDING TO THE BEAM POWER OF 130 kW, IF OPERATED AT DESIGNED REPETITION RATE OF 25 Hz.
J-PARC Project Newsletter #31 Feb., 2008
RADIATION SAFETY INSPECTION FOR THE RCS WAS CLEARED, BEING READY FOR THE NEXT STEP TO INJECT THE TEST BEAM TO BOTH THE NEUTRON PRODUCTION TARGET IN THE MLF AND MR
J-PARC Special News and J-PARC Newsletter No.30 dispatch, Nov. 1, 2007
The accelerator group succeeded in accelerating the beams from the Linac
to the design beam energy of 3 GeV via the Rapid-Cycling Synchrotron
Special news from J-PARC project on 2007.10.31.
J-PARC Project Newsletter #30 Oct. 30, 2007
THE RCS STARTED THE BEAM COMMISSIONING AS SCHEDULED
INTERLOCK SYSTEMS ARE READY FOR THE BEAM COMMISSIONING OF THE RCS
J-PARC newsletter #29 July 23, 2007
THE BEAM COMMISSIONING OF THE RCS IS COMING SOON.
THE LINAC IS READY TO INJECT, WHILE THE RCS IS TRYING TO SOLVE THE ELECTROMAGNETIC COMPATIBILITY ISSUE WITH ALL THE ACTIVE ELEMENTS.
J-PARC newsletter #28 May 28, 2007
THE LINAC ACCELERATED THE NEGATIVE HYDROGEN BEAM TO THE DESIGN ENERGY OF 181 MEV THREE MONTHS BEFORE SCHEDULED.
J-PARC Newsletter No.27 dispatch (Feb 8, 2007)
THE LINAC BEAM COMMISSIONING STARTED AS SCHEDULED,ACCELERATING THE BEAMS UP TO 50 MEV BY THE END OF 2006.
J-PARC newsletter #26 Oct. 19, 2006
THE RADIATION SAFETY AUTHORITY ISSUED THE PERMISSION FOR THE J-PARC CENTER TO START THE BEAM COMMISSIONING.THE RCS RF SYSTEM WAS SUCCESSFULLY POWER-TESTED FOR 1,000 HOURS.
J-PARC newsletter #25 31 July, 2006
THE J-PARC RING RF TEAM IS BREAKING THROUGH MANY TECHNOLOGICAL DIFFICULTIES
J-PARC newsletter #24 17 May 2006
THE RING RF TEAM IS FOCUSING ON FINDING THE METHOD OF CUTTING THE MAGNETIC ALLOY CORES, WHICH CAN STAND THE LONG-TERM HIGH POWER LOADING.
J-PARC Newsletter #23 Feb. 1, 2006
THE INSTALLATION OF THE ACCELERATOR COMPONENTS IS IN PROGRESS FOR ALL THREE ACCELERATORS, WHILE SOME R&D IS STILL NECESSARY FOR SOME COMPONENTS INSTALLATION OF CONTROL SYSTEMS FOR LINAC IS IN PROGRESS.
J-PARC Newsletter #22 Oct 28, 2005
THE CERAMICS VACUUM CHAMBERS FOR THE BENDING MAGNETS OF THE 1-MW RAPID-CYCLING SYNCHROTRON ARE NOW UNDER MASS PRODUCTION
J-PARC Newsletter #21 Aug., 2005 THE RFQ LINAC AND DTL WERE TRANSPORTED FROM KEK TSUKUBA SITE TO JAERI TOKAI SITE.
J-PARC Newsletter #20 May, 2005
REPORTS FROM ALL THE FRONTLINES OF THE ACCELERATOR CONSTRUCTION BATTLEFIELD
J-PARC Newsletter #19 Feb, 2005
|